so assuming the rate of interest is effective,,, lets find out the accumulated value of both the projects,,
Project 1: 111 (already given)
Project 2: 55(1.11)^0.5 + 55 = 112.95,,, implying project 2 is better
OR it can also be done via Present value approach:
Project 1: 111(1.11)^-1 =100
Project 2: 55(1.11)^-0.5 + 55(1.11)^-1 = 101.75,,, implying project 2 is better